Tony Little blasted for OK-ing $12,800 SEDD payments without board approval
Staff Reports · August 14, 2025

A request by Southside Economic Development District (SEDD) President Tony Little to authorize the final $12,889.66 payment to a contractor for renovations on the Arizona Street project has triggered controversy, with some board members insisting the work remains incomplete and raising concerns about possible mold in the building.
The payment, earmarked for contractor Ron Calhoun, was part of a $36,000 renovation contract awarded to RK Construction.
Last month, Little issued more than $24,000 to RK Construction in payments toward the project.
On Monday, Little asked the city’s finance department to cut the final check immediately, even though the board had not voted to accept the project as complete and it was not included on the Monday agenda.
In his email, Little said, "If there is any way these could be cut today, it would be greatly appreciated."
When the board met again in September, the final payment would have been received.
Board member Minister T.J. Stevenson, appointed to the SEDD by Mayor Friday Ellis, objected to the payout, stating that Calhoun’s work was “substandard” and that significant items from the project scope remained unfinished.
Stevenson also claimed mold was present in the facility and said she has asked the city inspector to evaluate the property. She reported Tuesday that, at her request, the mayor’s office halted the payment until a full punch list of remaining work could be signed off by all ten SEDD board members.
During Monday’s meeting, Little defended his position, telling the board the building was “complete” except for two air conditioning units and related electrical work.
Calhoun insisted that his company had fulfilled its bid specifications, including painting, cleanup, lighting, and ceiling replacement.
Stevenson, however, countered that list of what she described as incomplete work. She said painting was of poor quality, some molding was missing, and some items—like a new vanity—were billed but not delivered. She questioned two $750 charges for ordinary household toilets.
Concerns about mold were raised by member Roosevelt Wright, Jr. who said he observed Hispanic workers painting over what appeared to be mold during a site visit. Calhoun responded that the affected areas had been treated with mold control and sealed with primer, a process he described as standard.
The final payment request was not listed on Monday’s agenda, and no vote was scheduled to approve project completion. Critics note that Little submitted paperwork to the city suggesting the board had previously approved the payment in its adopted budget, though the budget contains no line item for the renovation. He also directed that the check be made payable to AHAAYAH-CDC, a nonprofit entity controlled by Calhoun.
Little has faced prior criticism for processing payments without board authorization. Last month, he requisitioned and delivered three separate $500 checks without the treasurer’s signature or board approval.
For now, the Arizona Street project remains unfinished, with the building’s readiness—and the fate of the final payment—still in dispute.
Filed under Local News
Back to the front pageRelated from the archives
Local News · October 3, 2025
SEDD Board split on suspending Little amid harassment, kickback allegations probeLocal News · January 12, 2023
SEDD elects Little, charts course for new year without TheusLocal News · August 26, 2021
Little appointed to SEDD BoardLocal News · October 17, 2025
Little still SEDD president, despite sex and kickback claims; Woods backs downLocal News · October 17, 2025
Will "Brown Bombers" survive Tony Little issue?