Sunday, November 22, 2026Vol. LVII · No. 46
Monroe Free Press — Fighting corruption and exposing injustice since 1969

Local News · Local News

Attorney General says contract with black company is valid, affirms I-20 authority to OK project

Staff Reports · May 28, 2026

Rev. James James says the I-20 board has been "vindicated" by the AG decision, but questions why, despite the opinion, the city has still refused to release the first check for $502,036.61 . McCallister said he would release funds if the AG's office proved him wrong. As of May 29, 2026, no check has been released.

Despite receiving an attorney general's opinion supporting the I-20 Board's contract with a Black contractor two weeks ago, the city has not, as of May 29th, written the check.

On May 15, 2026, a definitive legal ruling from the Louisiana Attorney General has solidly backed the I-20 Economic Development Board’s $4.5 million infrastructure contract. Despite the ruling, Monroe Mayor Friday Ellis and City CEO and Chief Engineer Morgan McCallister continue to block the project’s initial payment despite the state obliterating their legal arguments.

The conflict stems from a Cooperative Endeavor Agreement (CEA) approved by the I-20 Board to fund drainage and roadway improvements for a housing development proposed by Black business leaders Alven Square and Charles Theus . McCallister, acting as chief operating officer and engineer for the city, previously halted a $502,036.61 invoice submitted by the developers' company, DZE, claiming the project was illegal.

The standoff has been heavily charged with accusations of racial bias, as it marks the first time the I-20 Board has ever funded a project with a Black developer. During a heated board meeting, the racial tension boiled over when board member Rev. James Jackson directly challenged McCallister, stating, “You only have one real problem—and that is they don’t look like you. That’s the real problem.”

McCallister responded with an emotional, preemptive defense, retorting to the board, "I guess you are going to say, I'm a racist." He then turned directly to a reporter for the Ouachita Citizen and declared, “You can quote me, the racist said, I will never write a check for $300,000 to Charles Theus.”

The Attorney General’s Findings

In a formal opinion issued by the Office of Attorney General Liz Murrill and posted on the AG's public website, the state thoroughly rejected the city administration's legal objections. The binding document outlines four major conclusions that clear the project for funding:

Lawful Economic Development Project: The AG concluded that under Louisiana’s Cooperative Economic Development Law, participation in a residential subdivision qualifies as a legitimate "economic development project". The law explicitly includes housing and infrastructure as authorized industries to stimulate local economies.

Funding Outside District Boundaries Permissible: The AG determined that the I-20 Board may utilize state sales tax increment financing for construction physically located outside of, but adjacent to, the designated Garrett Road Economic Development Area. State statute allows for funding public works "within or about" the district.

No Legislative Budget Restrictions: The opinion found that the district is not restricted to specific past project descriptions by the Joint Legislative Committee on the Budget (JLCB). The JLCB’s active authorizations extend through December 31, 2033, and permit any economic development costs lawful under state act.

Legality of Bond Proceed Usage: Finally, the AG ruled that the district can legally utilize its Series 2019 Bond proceeds to fund this residential infrastructure project, provided the board maintains a reasonable expectation of a public return.

"We Have Been Vindicated"

The state's opinion brought swift reaction from board members who had previously clashed with McCallister over what they termed a "premeditated" and racially motivated blockade of a Black-owned enterprise.

“We have been vindicated,” stated I-20 Board Member Rev. James Jackson, following the release of the state's review. Jackson had previously asserted that the city's engineering department possessed absolutely no legal authority to overrule or pocket-veto the majority votes of the independent I-20 Board.

The Standoff Continues

Despite the Attorney General’s opinion being officially handed down on May 15th, the first draw check to DZE remains unreleased.

McCallister had previously pledged to the board that if the state opinion determined the project was within legal parameters, he would "be the first to stand before you and I will apologize and I will have a check cut." However, despite his public promises and the definitive ruling from the state's highest legal office, McCallister has dug in his heels. Because the city administration continues to withhold its sign-off, the vital corridor improvements remain entirely stalled in limbo.

Filed under Local News

Back to the front page

Related from the archives